CP400 Series
12
instruction manual for Type VSX4 Slam
shut for adjustment and maintenance of
the slam shut.
The range of allowable pressure settings
for the primary regulator is stamped on
the nameplate. If the required setting is not
within this range, substitute the correct
spring (as shown in Table 5). If the spring
is changed, change the nameplate to
indicate the new pressure range.
A pressure gauge should always be used
to monitor downstream pressure while
adjustments are being made.
Adjustment
To increase the outlet pressure setting of the
regulator, the adjusting screw of the loading regulator
(key 18, Figure 15) must be turned clockwise. This
requires loosening the locknut (key 19). To reduce
the outlet pressure setting, turn the adjusting screw
counterclockwise. Retighten the locknut. A pressure
gauge should always be used to monitor downstream
pressure while adjustments are being made.
CAUTION
Do not remove the locknut or adjust the
spring to produce an outlet pressure
setting outside the range of 1 to 20 psig /
69 mbar to 1.4 bar.
CP400 Series with Integral Monitor
When adjusting the primary regulator and Integral
Monitor for operation, ensure that the pressure
differences between the primary regulator and the
Integral Monitor shown in Tables 7 and 8 are observed.
For example, if the primary regulator setpoint is set
at 8 inches w.c. / 20 mbar, then the Integral Monitor
should be set at a minimum of 14 inches w.c. /
35 mbar or higher.
To test the Integral Monitor operation, the primary
regulator setpoint must be adjusted above the Integral
Monitor’s setpoint to simulate a failure of the primary
regulator. If the spring range of the primary regulator
is sufciently high, it can simply be adjusted above the
Integral Monitor’s setpoint by following the adjustment
procedure for the primary regulator. Otherwise, a
different spring with a setpoint higher than the Integral
Monitor’s setpoint must be installed to check the
operation of the Integral Monitor.
CP400 Series with Slam shut
When adjusting the primary regulator and slam shut
for operation, refer to Table 9 for the OPSO setpoints
and Table 10 of OPSO and UPSO setpoints of the
slam shut for the given regulator spring ranges.
!
WARNING
In the case of a downstream line break,
numerous factors affect the capability to
evacuate gas from the pipeline. These
factors include the distance of pipe
to the break, the diameter of the pipe,
size of the break and the number of
restrictions, such as valves, elbows and
bends, downstream of the regulator and/
or slam-shut device. Due to these factors
additional protections should be installed
to stop ow in the event of a line break.
CAUTION
Equipment installed downstream the
Type VSX slam-shut device can be
damaged if the following procedure for
resetting the Type VSX slam-shut device is
not followed. This equipment includes the
integral Type VSX/regulator congurations.
Step 1:
To properly reset the Type VSX slam shut after
it has been tripped to the closed position, a at-
head screwdriver must be inserted into the position
shown in Figure 8 on the backside of the reset
button (key 30, Figure 8).
Step 2:
The screwdriver should be slowly rotated to gradually
pull the reset button (key 30) away from the Type VSX
device. This slow movement allows for a slow bleed
of the pressure across the Type VSX slam-shut’s disk
and seat area. The operator should be able to hear the
pressure bleeding through the system.
Step 3:
• When the pressure has equalized and the air
bleeding sound has dissipated, the reset button
(key 30) should be pulled completely away from
the Type VSX slam-shut device by hand until the
internal shut-off mechanism has been re-latched.