Page view 8
7
ZB Series
Application guide
Crankcase heater
Single-phase scroll compressor does not require installation of
a crankcase heater.
When the refrigerant charge exceeds the values listed in the
following table, or, when the refrigerant is charged at-site, a
crankcase heater is necessary for the three-phase compressor.
Compressor Models Refrigerant Charge(kg)
ZB15-ZB45 4.5
ZB50-ZB88 7.2
ZB92-ZB11M 7.7
Pressure controller
To ensure the safe operation of the refrigeration system, Emerson
suggests that all systems be equipped with high- and low-pressure
switches.
See the following table for the recommended setting values (unit:
bar, gauge pressure).
Control type R22 R404A/507 R134a
High pressure (maximum) 26 30 18
Low pressure (minimum) 1.7 1.15 0.3
Gas-liquid separator
Copeland scroll compressor has a greater capacity to resist liquid because
of some inherent characteristics. It is possible that the gas-liquid
separator does not need to be used in most of the systems. However, it is
suggested that the gas-liquid separator be used when:
*
a large quantity of the liquid refrigerant in the system returns
continuously into the compressor within a period of regular stop
*
there is defrosting
*
there is a variable load regardless of the charged quantity of refrigerant
in the system
*
it is impossible to control the liquid-return phenomenon or wet start
because of the dilution of lubricating oil
If the gas-liquid separator is used in the system, it is suggested that the
dimension of the return oil orifice should be within 1-1.9mm. Also, the
filtering area of the protecting screen should be large enough, and its
mesh size not below 30x30 (diameter of 0.6mm). It is not advisable to use
screen finer than 30x30 mesh in the system anywhere in order to protect
the orifice from being blocked by debris.
Drying filter and humidity indicator
The filter drier installed in the liquid piping should be large enough and
adequate for uninterrupted operation. The dehumidifier should be
selected according to the flow rate of the refrigerant. Do not use
dehumidifiers that can turn into liquid state after absorbing a large
quantity of wet steam, such as potassium chloride. It is suggested that
porous block dehumidifiers are used to absorb the wet steam or acid and
prevent metal fragments from invading. The filter drier should be
installed after a second vacuum operation has been carried out. The sight
glass for the humidity indicator should be installed in a clearly visible
position on the liquid piping, in order to facilitate the checking of
refrigerant flow rate.
40
Installation of the crankcase heater
Page view 8