COMMISSIONING
Operations concerning the integral slam shut version are in italic.
All interventions on equipment should only be performed by
qualified personnel
PRELIMINARY VERIFICATIONS
Start-up positions
• Inlet and outlet valves
Æ Closed
Verify the absence of pressure between inlet and outlet valves
• Slam shut valve plug
Æ
Closed
• Pilot A
Æ Unloaded
• Restriction B
Æ START position
Slam shut set point verification
Using the atmospheric valve, inject a pressure equal to the pressure
required for the regulator
• 1
st
release relay stage
Æ Set (Stage 1)
• Slam shut valve plug
Æ Open (Stages 2 & 3)
Æ Progressively increase the pressure to
reach tripping
Æ Adjust setting if necessary (NTAOS2)
Note the set point value on the equipment
or mark it on a commissioning document
Positions before commissioning
• Impulse line isolating valve
Æ Open
• Impulse line atmospheric valve
Æ Closed
• Slam shut valve plug
Æ Closed
• Servicing valve
Æ Closed
The equipment is ready for commissioning
COMMISSIONING (Act slowly)
• Inlet valve
Æ Open very slowly
• 1
st
release relay stage
Æ Set (Stage 1)
• Slam shut valve plug
Æ Bypass (Stage 2)
Æ Open (Stage 3)
B22
B20
Triggered
position
Stage 1
Stages 2 and 3
• Servicing valve
Æ Open slightly
• Pilot
Æ Screw to set outlet pressure
• Outlet valve
Æ Open slowly
• Restriction
Æ Set to "RUN" by successive fractions 2, 4 or 6
• Servicing valve
Æ Closed
The equipment is commissioned
It is recommended to seal the release relay